Phase Two Headway

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remediation work continues on the existing storm water management pond. The area will become the new Publix building pad and parking lot. Storm piping is being buried as we continue work on the new detention pond. Landscaping is in progress throughout the site.

Structure Progresses With Concrete Pour

Because of the extreme heat we are experiencing this summer, our team decided to pour the first concrete slab at night, when temperatures are more accommodating.

As the sun rose the following morning, our first slab was in place.

Our team is continuing demo and prep work throughout the site.

We are placing stone in the underground detention pond, which will filter storm water and protect against flooding.