Phase 2 Progresses on Schedule

This will be a busy week, with activities moving forward on and off the job site. We are laying asphalt on the Publix parking lot and a patio is being poured at Panera Bread. Just offsite, preparations are being made for the widening of Cox Creek and Hough Road. The long awaited pylon sign has arrived and is being erected.

Phase Two Headway

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remediation work continues on the existing storm water management pond. The area will become the new Publix building pad and parking lot. Storm piping is being buried as we continue work on the new detention pond. Landscaping is in progress throughout the site.